Project: St. Catherines Primary School Newcastle

Project value: £100,000
Project style: Consultant Design
Client: St Catherines School
Project Duration: Aug 2012 – Nov 2012

The above project consisted of three phases of work. We co-ordinated the required working areas with the School as various areas were still occupied:

  • Phase 1 consisted of the replacement of the existing gas fired heating & hot water plant, BMS upgrades to suit the new installation and the co-ordination of electrical installation works.
  • Phase 2 consisted of the replacement and installation of new pipework and fan convectors to serve the infants area.
  • Phase 3 consisted of the replacement of existing pipework to nursery classrooms.